Sunday, May 3, 2009

Quick update

Hello Dreamers - apologies for the delays - quite a lot has been happening the last month and a half - will try to compress into a few lines:

- all eaves and eaves brackets have been installed
- three out of four walls have been undercoated
- wall insulation has been installed
- noggins for the verandah have been installed
- ducted vaccuming system is almost fully installed
- quads have been put on most windows and doors

Currently the plasterer is installing the ceiling batons in readiness for the plaster to be installed this coming Wednesday. Matt from MJC Plastering and Painting has been working hard in getting it installed - including placing extra beams in the ceiling to be able to cater for the weight of the corninces. Hopefully the main plaster will be installed by this Saturday so we should have defined rooms inside! Getting close now.

Plan now is for installation of the floorboards by Steve starting the 17th of May - by which time hopefully all the plaster and fancy work is completed.

I'll upload the latest round of photos before Wednesday so you can get an idea on the progress being made.

Thanks for your patience,

CJ